Wednesday, 2 February 2011

Blackford Avenue delays

Blackford Avenue
Roadworks in Blackford Avenue, scheduled for completion by the end of November, are now scheduled for completion by February 14th.  Work began at the beginning of September.

For the technically minded, the roadworks are the final ' joint bay connections' in relation to Scottish Power's 275kv mains upgrade.  Alas, a gas leak and the winter snow delayed the completion.


The latest I have is that jointing work is due to be completed by the middle of next week with the resurfacing completed by the weekend.  Normal traffic flow should be in place on Valentine's Day!


Ominously, though, I understand there are separate excavations further south investigating a further reported gas leak.

1 comment:

Poetry of the Day said...

oh that is awesome, feb 14 is so near
- <3 Famous Poetry about life

Featured post

Local resident Jim Sillars in the news

Former deputy leader of the SNP Jim Sillars lives locally.  He has been speaking out on a couple of issues recently. First, here is today...